Re: Koralm Railway

#31
post #15

Earlier quoted context omitted.

Agreed, it was just important to me to point it out, since staying within such a massive budget on such a long timeline is a rare achievement.

Considering the original title is just the name of the railway, and I do not think “within budget” is editorializing, I think the commenter is being overly pedantic

I opened the article expecting to see news about the budget and how they stayed within it, since that SEEMS like the biggest surprising news in a project like this. How is that overly pedantic?

Re: Koralm Railway

#32
post #16

Earlier quoted context omitted.

To contrast, HS2 here in the UK has cost £40 billion (€45 billion) to date with a further £25 billion (€28 billion) allocated, for a largely superterranean route of 230km.

As badly as HS2 has been run, apart from the tunnel length (where HS2 has not too much more than this project) these projects are night and day different. Not just that HS2 Phase 1a/1b is almost double the length and significantly higher design speed (360km/h vs 250km/h), but they are in a different league in terms of civil engineering from the info I can see - this seems to have less than 80 structures (overpasses,…

> this seems to have less than 80 structures (overpasses, bridges, underpasses etc.) whereas HS2 has 175 bridges and 52 viaducts.

Doesn't tunnel beat any of those structures in terms of cost/complexity?

Re: Koralm Railway

#33
post #25

First, this is a massive accomplishment. When I looked at the Wiki page: https://en.wikipedia.org/wiki/Koralm_Railway ... it looks like a multi-multi-multi-phase project. Hats off to making this work. Second, I noticed how long it took to build this tunnel: Koralm Tunnel -> https://en.wikipedia.org/wiki/Koralm_Tunnel It is 33km, and it took from 2008 to 2025 to build it. That is a damn long time! The Toei Oedo line i…

It is very strange that countries like Austria, Japan or Switzerland have some of the best rail systems in the world even though their bridge and tunnel requirements are huge. In the US building rail on any terrain seems to be more expensive than basically anything one can build in Austria.

Not strange at all! If you want to go by car you must build even more tunnels. Mountainous regions favor rail just like urban areas do. Furthermore, 19th century investments into rail still pay off in mountainous regions, because once you build a railway bridge or tunnel, you are kind of dumb not to use it. In the USA competition from trucks or cars is much tougher.

Re: Koralm Railway

#35
post #24

Earlier quoted context omitted.

7x longer for 11x the cost seems pretty good all things considered. Always thought it seemed like a waste to not also dig out a bunch of storage while we're down there. I'm sure there are good reasons we don't

It's not seven times longer. The Austrian line is 130km with 50km of tunnels. Length Tunnels Bridges Stations Cost Koralm 130km ~50km 100 12 €6b HS2 230km ~75km 100+ 4 €74b+ Obviously this does not give any indication of the complexity of each project. Tunnelling and building railway through a metropolis I would imagine is quite challenging.

Still seems insanely more expensive in the UK. I understand they have a higher cost to carry because their project is indeed more complex, but that's like a almost 13x more expensive variant, while not even being two times the length.

Re: Koralm Railway

#37
post #32

Earlier quoted context omitted.

As badly as HS2 has been run, apart from the tunnel length (where HS2 has not too much more than this project) these projects are night and day different. Not just that HS2 Phase 1a/1b is almost double the length and significantly higher design speed (360km/h vs 250km/h), but they are in a different league in terms of civil engineering from the info I can see - this seems to have less than 80 structures (overpasses,…

> this seems to have less than 80 structures (overpasses, bridges, underpasses etc.) whereas HS2 has 175 bridges and 52 viaducts. Doesn't tunnel beat any of those structures in terms of cost/complexity?

Not necessarily because no one lives underground and there are probably no existing things like property, gas lines, electricity lines, sewers, pipelines, roads, etc to avoid or reroute. And very little in the way of habitat.

The longest road tunnel in the world only cost about 100 million in the 90s for 25km so tunneling isn't always a gigantic Big Dig style clusterfuck.

In terms of legal complexity, it's fantastically easier than picking your way across and near thousands of individual plots of very expensive land owned by people with solicitors salivating at the potential fees, expensive private infrastructure, nature reserves and so on.

Re: Koralm Railway

#38
post #16
post #6

Earlier quoted context omitted.

It is mostly within budget, estimated in 2005 were 5.5 billion €, total cost as of today are 5.9 billion €, the difference being largely attributed to the pandemic and later addition of sections.

To contrast, HS2 here in the UK has cost £40 billion (€45 billion) to date with a further £25 billion (€28 billion) allocated, for a largely superterranean route of 230km.

In contrast, the 2nd Ave Subway extension here in NY cost $4.5 billion for 2.9 km

Re: Koralm Railway

#39
> Crossing the Koralpe massif more quickly and with more comfort. That’s what the future of train travel from Graz to Klagenfurt looks like. With the Koralm Railway, you will arrive at your destination even quicker. The fastest connection will shrink from three hours to just 45 minutes.

There aren't any big mountains between Graz and Klagenfurt. It's an hour on the Autobahn. That it took three hours by train... well, they just had shitty railroad? Best of luck, Southern neighbors!

Re: Koralm Railway

#40

First, this is a massive accomplishment. When I looked at the Wiki page: https://en.wikipedia.org/wiki/Koralm_Railway ... it looks like a multi-multi-multi-phase project. Hats off to making this work. Second, I noticed how long it took to build this tunnel: Koralm Tunnel -> https://en.wikipedia.org/wiki/Koralm_Tunnel It is 33km, and it took from 2008 to 2025 to build it. That is a damn long time! The Toei Oedo line i…

I'm guessing geology play a big part - Japan is mostly "new" rock, Alps mostly "old".