Earlier quoted context omitted.
"The Koralm Tunnel opened on the 14th of December 2025" ... wikipedia living in the future past :)
Haha, check who updated this article. Only afterwards I realized we're not past the 14th yet...
Koralm Railway
21–30 of 206 posts
Re: Koralm Railway
#22I know its a small nitpick, but I got unreasonably annoyed at the two "Financed by EU fund x" banners having different flag sizes, paddings, fonts etc. How is there no unifying design language for these?
Is there any design? It's just the flag and a title + subtitle. Also, the EU is the most efficient government in terms of overhead, and having seen some of it up close not wasting time or money on "unifying design languages" for every single funding billboard is very much EU style. Just copy-paste by some local authority in Powerpoint in most cases, I bet.
1: https://hadea.ec.europa.eu/programmes/connecting-europe-faci...
2: https://commission.europa.eu/document/download/3192a0ef-6bda...
3: https://ec.europa.eu/regional_policy/information-sources/log...
Re: Koralm Railway
#23Earlier quoted context omitted.
It is mostly within budget, estimated in 2005 were 5.5 billion €, total cost as of today are 5.9 billion €, the difference being largely attributed to the pandemic and later addition of sections.
To contrast, HS2 here in the UK has cost £40 billion (€45 billion) to date with a further £25 billion (€28 billion) allocated, for a largely superterranean route of 230km.
Always thought it seemed like a waste to not also dig out a bunch of storage while we're down there. I'm sure there are good reasons we don't
Re: Koralm Railway
#24Earlier quoted context omitted.
To contrast, HS2 here in the UK has cost £40 billion (€45 billion) to date with a further £25 billion (€28 billion) allocated, for a largely superterranean route of 230km.
7x longer for 11x the cost seems pretty good all things considered. Always thought it seemed like a waste to not also dig out a bunch of storage while we're down there. I'm sure there are good reasons we don't
Length Tunnels Bridges Stations Cost
Koralm 130km ~50km 100 12 €6b
HS2 230km ~75km 100+ 4 €74b+
Obviously this does not give any indication of the complexity of each project. Tunnelling and building railway through a metropolis I would imagine is quite challenging.Re: Koralm Railway
#25First, this is a massive accomplishment. When I looked at the Wiki page: https://en.wikipedia.org/wiki/Koralm_Railway ... it looks like a multi-multi-multi-phase project. Hats off to making this work. Second, I noticed how long it took to build this tunnel: Koralm Tunnel -> https://en.wikipedia.org/wiki/Koralm_Tunnel It is 33km, and it took from 2008 to 2025 to build it. That is a damn long time! The Toei Oedo line i…
Re: Koralm Railway
#26Earlier quoted context omitted.
It is mostly within budget, estimated in 2005 were 5.5 billion €, total cost as of today are 5.9 billion €, the difference being largely attributed to the pandemic and later addition of sections.
To contrast, HS2 here in the UK has cost £40 billion (€45 billion) to date with a further £25 billion (€28 billion) allocated, for a largely superterranean route of 230km.
Re: Koralm Railway
#27First, this is a massive accomplishment. When I looked at the Wiki page: https://en.wikipedia.org/wiki/Koralm_Railway ... it looks like a multi-multi-multi-phase project. Hats off to making this work. Second, I noticed how long it took to build this tunnel: Koralm Tunnel -> https://en.wikipedia.org/wiki/Koralm_Tunnel It is 33km, and it took from 2008 to 2025 to build it. That is a damn long time! The Toei Oedo line i…
Kanto is flat, it's the only region in Japan that could sustain feeding such a massive population and could allow building the first mega city on the planet.
Combine that with the massive engineering and rail experience Japanese have, and it's no surprise imho that combined with favorable geography they could build it quickly.
[1] https://upload.wikimedia.org/wikipedia/commons/2/28/Topograp...
Re: Koralm Railway
#28Earlier quoted context omitted.
To contrast, HS2 here in the UK has cost £40 billion (€45 billion) to date with a further £25 billion (€28 billion) allocated, for a largely superterranean route of 230km.
7x longer for 11x the cost seems pretty good all things considered. Always thought it seemed like a waste to not also dig out a bunch of storage while we're down there. I'm sure there are good reasons we don't
Re: Koralm Railway
#29First, this is a massive accomplishment. When I looked at the Wiki page: https://en.wikipedia.org/wiki/Koralm_Railway ... it looks like a multi-multi-multi-phase project. Hats off to making this work. Second, I noticed how long it took to build this tunnel: Koralm Tunnel -> https://en.wikipedia.org/wiki/Koralm_Tunnel It is 33km, and it took from 2008 to 2025 to build it. That is a damn long time! The Toei Oedo line i…
Being two separate tunnels, it also needs twice as much excavation work. It's also ~25x deeper than Toei Oedo (4000ft vs 157ft). At 4000ft the rock itself is 45-50C!
Re: Koralm Railway
#301998: Start of construction of the Koralm Railway
2008: Start of construction of the Koralm Tunnel
2018: Breakthrough Koralm Tunnel
2020: Final Koralm tunnel breakthrough
2025: This announcement (https://orf.at/stories/3414173/ in German)
https://infrastruktur.oebb.at/en/projects-for-austria/railwa...