How do you communicate if you won't hit an estimate?

news.ycombinator.com

41–50 of 51 posts

Re: How do you communicate if you won't hit an estimate?

#41
Don't guess at how long it takes to complete work. Plan what you think you need, and then do a week of stories. Based on your velocity, make a confidence interval of dates. Next week, do the same thing.

If they want a fixed date, take 60% of your velocity and you'll be pretty sure your math will work out to give you the project on time.

Anything not based on data is pulling numbers out of your ass, and it's hilariously disastrous every time.

Re: How do you communicate if you won't hit an estimate?

#42
post #15

How do you communicate if you won't hit an estimate? Immediately, with brutal honesty, and positively. 1. Immediately: Never delay communication. Most people will be less upset about the schedule than the fact that they weren't informed. 2. With Brutal Honesty: Explain exactly what's going on. You may end up with a pleasant surprise. "Oh, can we just have xyz then?" or "How can we reduce the scope?" or " How can we h…

Yep, this exactly. Your estimates will get better as you have more information, so keep everyone updated as you get into the thick of it. This is why Agile has daily standups. If you don't have a daily status call, do try to get into some sort of routine update.

It also helps if you know what is the highest priority and what can get sacrificed.

If you're late, talk about it in your retrospective. Taking time to look back will help you make better estimates in the future. Often times I gauge how reliable an engineer's estimate is based off of how many questions he/she asked me during the kick off meeting.

Re: How do you communicate if you won't hit an estimate?

#43
post #15

How do you communicate if you won't hit an estimate? Immediately, with brutal honesty, and positively. 1. Immediately: Never delay communication. Most people will be less upset about the schedule than the fact that they weren't informed. 2. With Brutal Honesty: Explain exactly what's going on. You may end up with a pleasant surprise. "Oh, can we just have xyz then?" or "How can we reduce the scope?" or " How can we h…

You're the fucking man or woman

"You're the man" is a non-gendered statement.

Re: How do you communicate if you won't hit an estimate?

#44
post #22

Earlier quoted context omitted.

This is horrible advice.

Why? Can you elaborate on why you feel that way and what you feel would be better advice?

I'm guessing the negative comment refers to "communicate this detailed hourly plan with your total estimate"

Providing an hourly schedule for a project as short as a week sounds completely crazy to me. Imagine how to pull that off for a month+ project. Maybe the sentence was phrased poorly.

Re: How do you communicate if you won't hit an estimate?

#45
post #15

How do you communicate if you won't hit an estimate? Immediately, with brutal honesty, and positively. 1. Immediately: Never delay communication. Most people will be less upset about the schedule than the fact that they weren't informed. 2. With Brutal Honesty: Explain exactly what's going on. You may end up with a pleasant surprise. "Oh, can we just have xyz then?" or "How can we reduce the scope?" or " How can we h…

You're the fucking man or woman

"That's really good!"

Re: How do you communicate if you won't hit an estimate?

#46
post #22

Earlier quoted context omitted.

This is horrible advice.

Why? Can you elaborate on why you feel that way and what you feel would be better advice?

Because sometimes it's a small task with a small time estimate that balloons out of proportion. You look sillier when your one day task balloons to five days, rather than your 10 day bundle of tasks balloons to 15, because a third-party library is poorly document and doesn't do what it claims to do in your specific context. Splitting the tasks doesn't make then go by faster.

Re: How do you communicate if you won't hit an estimate?

#49
post #15

How do you communicate if you won't hit an estimate? Immediately, with brutal honesty, and positively. 1. Immediately: Never delay communication. Most people will be less upset about the schedule than the fact that they weren't informed. 2. With Brutal Honesty: Explain exactly what's going on. You may end up with a pleasant surprise. "Oh, can we just have xyz then?" or "How can we reduce the scope?" or " How can we h…

As a PM, this would work for me.

Re: How do you communicate if you won't hit an estimate?

#50
One of the things that McConnell's "Software Estimation" repeats a lot is that estimates are _intervals_. I'm a bit surprised not many people here have mentioned that.

If you give a single number, there's a 100% chance that it's wrong -- you're never going to hit it exactly.

Instead, what you should be aiming for is to give an interval that is correct, say, 90% of the time (so still wrong 1 out of 10 times).

If you do it honestly, the intervals have to be much wider you than you are used to -- the "two weeks" you would usually say is realistically more between 8 working days and six weeks, with 90% confidence.

A major benefit of giving intervals to people instead of fixed numbers is that it makes it really clear that it's not a deadline and can't be treated as one.

If they tell you this is unacceptable, then only give the high number, and McConnell's book.