Live data from Hacker News

Higher usage limits for Claude and a compute deal with SpaceX

anthropic.com

151–160 of 519 posts

Re: Higher usage limits for Claude and a compute deal with SpaceX

#151

Earlier quoted context omitted.

One of the reasons I refuse to use xAI’s models is because of the outsized negative environmental impacts of the methane gas turbines. Now I have to avoid Claude too.

If you can make up an inconsequential arbitrary rationalization to not use a service then I’m sure you can do the opposite to convince yourself to use it. That’s what virtue signaling is I guess - the action you’re taking is pointless, the only point is to tell everyone you’re taking it therefore feed the narrative forward? The entire economy runs off gas turbines though this is the thing you boycott?

[dead]

Re: Higher usage limits for Claude and a compute deal with SpaceX

#153

Reading the comments here again surprises me how in an anti-Elon bubble most folks are. They are renting out spare Colossus 1 capacity. Colossus 2 is still coming online. Orbital data centers are really the plan in the next few years. XAi is still behind, but not a disaster considering how late they entered (and Elon’s unfortunate fixation on anime characters). SpaceX is extremely uniquely positioned to crush the res…

I struggle to understand how orbital data centers can make sense. Is it mainly for continuous solar energy? Surely this can't be enough to offset the costs of launching?

Re: Higher usage limits for Claude and a compute deal with SpaceX

#154

Earlier quoted context omitted.

One of the reasons I refuse to use xAI’s models is because of the outsized negative environmental impacts of the methane gas turbines. Now I have to avoid Claude too.

You realize natural gas is one of the more environmentally friendly methods of generating power. Lots of work went into moving to natural gas generation to improve the environmental impact for electricity generation. This is nothing like burning coal.

This natural gas burning is suited too close to where people live.

Re: Higher usage limits for Claude and a compute deal with SpaceX

#155

Colossus 1 datacenter is the one using illegal power, is poisoning the air for poor communities near Memphis, and is potentially poisoning the water. It's likely the additional demand on the grid will cause massive blackouts during extreme weather events, putting residents at further risk. https://en.wikipedia.org/wiki/Colossus_(supercomputer)#Envir... So you can put Anthropic on your list of companies that like to t…

Illegal is a strong term here. While the wiki link you included indicates there might be some permitting nuances, I've seen nothing claiming the power is "illegal."

xAI removed its illegal gas turbines and obtained permits for the others only after being sued by the Southern Environmental Law Center. They then built another unpermitted site (Colossus 2) across the state line in Mississippi, and they are being sued again. [0]

"The company began operations at its first site, Colossus 1, in June of 2024 and used as many as 35 unpermitted gas turbines to power the facility. Despite receiving intense public pushback over the use of illegal turbines and the lack of public input and transparency around Colossus 1, xAI officials said it planned on “copying and pasting” its unlawful turbine strategy to power Colossus 2."

"xAI removed its unpermitted turbines at the Colossus 1 data center after SELC, on behalf of the NAACP, sent a notice of intent to sue under the Clean Air Act. The company obtained permits for its remaining 15 turbines."

[0] https://www.selc.org/news/xai-built-an-illegal-power-plant-t...

Re: Higher usage limits for Claude and a compute deal with SpaceX

#157
post #155

Earlier quoted context omitted.

Illegal is a strong term here. While the wiki link you included indicates there might be some permitting nuances, I've seen nothing claiming the power is "illegal."

xAI removed its illegal gas turbines and obtained permits for the others only after being sued by the Southern Environmental Law Center. They then built another unpermitted site (Colossus 2) across the state line in Mississippi, and they are being sued again. [0] "The company began operations at its first site, Colossus 1, in June of 2024 and used as many as 35 unpermitted gas turbines to power the facility. Despite…

[flagged]

Re: Higher usage limits for Claude and a compute deal with SpaceX

#158
post #136
post #123

Earlier quoted context omitted.

I dedicate a significant amount of time to defining the precise actions that agents should perform (PRD/ADR). I break down the feature sets into Milestones and slices (tasks). These tasks are small, well-defined, and scoped. I have a prompt template that the “architect” agent prepares whenever I want to initiate a new feature. This ensures that the prompt structure remains consistent and standardized over time. The g…

I have found that it uses a lot more tokens if I give it a very detailed todo and loop over every task 1 by 1. I now keep it to phases with detailed tasks underneath and use /loop over the phases and it uses a lot less. I also manage the context windows and tend to clear it often to keep it under around 200k (or less depending on project size)

Yeah, I do that too. Essentially, the system I described begins working on a task that is small enough and clearly defined. Each “slice” in a milestone usually have 5-10 subtasks (for instance, Slice E1 has P1...P6 subtasks). The orchestrator then receives the prompt to implement E1-P1.

Re: Higher usage limits for Claude and a compute deal with SpaceX

#159
post #111
post #14

Anthropic renting out the data center Elon built for Grok is the kind of plot twist you can't make up.

It was pretty obvious to me that the merger was a way of quietly shutting xAI down in a way that keeps investors happy. With it also being used as a vehicle to offload the Twitter debt to the public, he certainly has good accountants.

Not a merger, right, unless I missed something (admittedly skimming).

Re: Higher usage limits for Claude and a compute deal with SpaceX

#160

For those who haven't been following the build out. xAI has added about 500MW of nvidia gpu capacity in ~April and will add another 500MW before the end of the year totaling about 2GW.

Source on this?

Following various X posts, asking Grok to check my memory. https://grokipedia.com/page/Colossus_supercomputer backs this up.
Post reply on HN