How I estimate work

seangoedecke.com

131–140 of 326 posts

Re: How I estimate work

#131

After owning a product, I've developed a lot of sympathy for the people outside of engineering who have to put up with us. Engineers love to push back on estimates, believing that "when it's done" is somehow acceptable for the rest of the business to function. In a functioning org, there are lot of professionals depending on correct estimation to do their job. For us, an accurate delivery date on a 6 month project wa…

I agree. Software engineering is basically the only industry that pretends this is professionally acceptable. Imagine if government staff asked when a bridge would be done or how much it would cost and the lead engineer just said "it's impossible to estimate accurately, so we wont. It's a big project tho". Estimating in software is very hard, but that's not a good reason to give up on getting better at it

They miss estimates all the time though? It’s an observable fact

There is a bridge in my town that is finally nearing completion, hopefully, this year. It was estimated to be completed 2 years ago.

This changes when it’s a project that has fewer unknowns, where they’ve built the same thing several times before. The same is true in software.

Re: How I estimate work

#132

After owning a product, I've developed a lot of sympathy for the people outside of engineering who have to put up with us. Engineers love to push back on estimates, believing that "when it's done" is somehow acceptable for the rest of the business to function. In a functioning org, there are lot of professionals depending on correct estimation to do their job. For us, an accurate delivery date on a 6 month project wa…

With respect, I think this approach is actually harmful to everyone in the org because you're trying to twist reality to fit a premise that is just impossible to make true: that estimates of how long it takes to build software are reliable.

The reluctance to accept the reality that it cannot be made true achieves nothing positive for anybody. Rather it results in energy being lost to heat that could otherwise be used for productive work.

This isn't about respect between functions, this isn't about what ought to be professionally acceptable in the hypothetical. It's about accepting and working downstream of a situation based in objective truth.

Believe me, I wish it were true that software estimates could be made reliable. Everyone does. It would make everything involved in making and selling software easier. But, unfortunately, it's not easy. That's why so few organisations succeed at it.

I don't present easy answers to the tensions that arise from working downstream of this reality. Yes, it's easier to make deals contingent on firm delivery dates when selling. Yes, it's easier to plan marketing to concrete launch dates. Yes, it's easier to plan ahead when you have reliable timeframes for how long things take.

But, again unfortunately that is simply not the reality we live in. It is not easy. Flexibility, forward planning and working to where the puck is going to be, and accepting redundancy, lost work, or whatever if it never arrives there is part of it.

That I think is what people in different functions are best served rallying and collaborating around. One team, who build, market and sell software with the understanding that reliable estimates are not possible. There simply is no other way.

Re: How I estimate work

#133
This is clever advice, to first find out what estimate is tolerable to management and then adapt your design to fit. It's sort of like what the makers of Basecamp, in their book Getting Real, say in chapter 7, "Fix Time and Budget, Flex Scope"https://basecamp.com/gettingreal/02.4-fix-time-and-budget-fl...>.

I wonder if it was a mistake to ever call it "engineering", because that leads people to think that software engineering is akin to mechanical or civil engineering, where you hire one expensive architect to do the design, and then hand off the grunt work to lower-paid programmers to bang out the code in a repetitive and predictable timeline with no more hard thinking needed. I think that Jack Reeves was right when he said, in 1992, that every line of code is architecture. The grunt work of building it afterward is the job of the compiler and linker. Therefore every time you write code, you are still working on the blueprint. "What is Software Design?"https://www.bleading-edge.com/Publications/C++Journal/Cpjour...>

Martin Fowler cites this in his 2005 essay about agile programming, "The New Methodology"https://www.martinfowler.com/articles/newMethodology.html>. Jeff Atwood, also in 2005, explains why software is so different from engineering physical objects, because the laws of physics constrain houses and bridges and aircraft. "Bridges, Software Engineering, and God"https://blog.codinghorror.com/bridges-software-engineering-a...>. All this explains not only why estimates are so hard but also why two programs can do the same thing but one is a thousand lines of code and one is a million.

I came into programming from a liberal arts background, specifically writing, not science or math. I see a lot of similarities between programming and writing. Both let you say the same thing an infinite number of ways. I think I benefitted more from Strunk and White's advice to "omit needless words" than I might have from a course in how to build city hall.

Re: How I estimate work

#134
The most memorable estimation technique I came across when I started out as a software engineer was "two days or less?".

Our team would simply gather around, go through the tasks that were agreed with the business and on count of three, each of us simply raise a thumbs up if we thought we could ship it within two days - otherwise thumbs down.

It generally implied we collectively thought a task would take more than two days to ship, it may require breaking down, otherwise it’s good to go.

Re: How I estimate work

#135
post #121

Earlier quoted context omitted.

If you hired someone to do some work on your house, and they refused to give an estimate, would you be happy? If you had a deadline - say thanksgiving or something - and you asked “will the work be done by then” and the answer was “I’m not going to tell you” would you hire the person? The no estimates movement has been incredibly damaging for Software Engineering.

Anybody who worked with a local contractor knows that their estimate and the reality has no correlation. When you ask for a firm estimate, you are basically asking to be lied to, and the contractor happily complies by telling you a lie.

These are just bad contractors. I used to work for a remodeling company. We came in under time on the vast majority of projects because the guy who ran the company knew what he was doing and built slack into the schedule.

Re: How I estimate work

#136
I read what the author is saying as “time is fixed, so I adjust the scope.” The problem is when product or management is demanding both fixed time and fixed scope. “Here’s a list of requirements (which are under defined and we will change without giving you a chance to estimate) and a set of figmas you must implement for those requirements (and also we will look at the finish product and decide not to give you any extra time to make changes we want or build a breakpoint not defined by the Figma that we demand), no how much time with this I’ll-defined, fixed-scope take?”

Fixed time and fixed scope is essentially impossible, except in trivial cases. What I read the author saying is that he chooses to make it fixed time and has flexibility around scope in his work, because the requirements are more like loose descriptions than a description of exactly what a product should do, while ignoring edge-cases. That sounds like a nice situation. And a perfectly fine way to manage an engineering team. But it also sounds a bit to me like an abdication of responsibility to the engineering team by product, to allow the engineering team to decide what exactly the scope is. Again, that’s a perfectly good way to do it, but it means that product can’t come back and say “that’s not what I was expecting, you didn’t do it.”

I don’t think the author really tackles estimation here, nor the reasons why estimation is a hard and controversial issue, nor what junior engineers are looking for when googling “how do I estimate?”

The real reason it’s hard in this industry is that in general, product controls both scope and time, which are the two major dials by which delivery is managed, but abdicate responsibility for them by going an ill-defined but nonetheless more fixed (and unyielding) scope than described in this article, then demanding engineers give them specific date estimates to which they’ll commit, and work free overtime if they turn out to be wrong.

The author correctly defines a way to resolve this conflict: give engineering more say over scope—but fails to recognize that the root cause is not poor estimation, but rather that product or management denies engineering much say over scope past the initial estimation, and then demands they set fixed dates they commit to before enough is known. Death march projects, in my experience, are generally a failure of product, not engineering.

Re: How I estimate work

#137

One thing I think is missing is an understanding of why there is such a top-down push for timelines: because saying "we aren't sure when this feature will be delivered" makes sales people look like they don't know what they are talking about. Which.... well. They would much rather confidently repeat a date that is totally unfounded rubbish which will have to be rolled back later, because then they can blame the engin…

If you hired someone to do some work on your house, and they refused to give an estimate, would you be happy? If you had a deadline - say thanksgiving or something - and you asked “will the work be done by then” and the answer was “I’m not going to tell you” would you hire the person? The no estimates movement has been incredibly damaging for Software Engineering.

When there are huge unknowns, such as in the case of a remodel where who knows what you might find once the drywall is removed, then yes. I happily worked with a contractor on a basement renovation with no estimate for this exact reason.

If it’s something where they have fewer unknowns and more control and lots of experience building the same thing, then I would expect an estimate: building a deck, re-roofing a house, etc

Re: How I estimate work

#138
Whenever this comes up I feel like I work on completely different kinds of software than most people here. (Giant, backend, distributed systems projects at FAANG)

I’ve never worked on anything large in software where the time it will take can be reasonably deduced at the accuracy some people here seem to assume possible. The amount of unknown-unknowns is always way way too large and the process of discovery itself extremely time consuming. Usually it requires multiple rounds of prototypes, where prototypes usually require a massive amount of data transferred to adequately mine for work discovery.

The best you can do is set reasonable expectations with stakeholders around:

- what level of confidence you have in estimates at any point in time

- what work could uncover and reduce uncertainty (prototypes, experiments, hacks, hiring the right consultant, etc) and whether it is resourced

- what the contingency plans are if new work is discovered (reducing specific scope, moving more people (who are hopefully somewhat ramped up), moving out timelines)

Re: How I estimate work

#139
post #69

Earlier quoted context omitted.

> Trim features, push date, bring in extra help, or crunch. There are problems with all of these. The company knows they can sell X of the product for $Y (often X is a bad guess, but sometimes it has statistical range - I'll ignore this for space reasons but it is important!). X times Y equals gross profit. If the total costs to make the feature are too high the whole shouldn't be done. If you trim features - the aff…

I would settle for accurate estimates being a requirement if sticking to the estimate and allocations is as well. Every project I've been a part of that has run over on timeline or budget had somebody needling away at resources or scope in some way. If you need accuracy to be viable, then the organization cannot undermine the things that make it possible to stay on track.

Also, if you need accuracy stay away from questionable vendors of 3rd party products, as much as possible since they are chaos generators on any project involved.

In my work we have our core banking system designed in 80s on top of Oracle DB so everything is just boxes around it, with corresponding flexibility towards modern development methodologies. The complexity of just doing a trimmed copy of production servers for say user acceptance test phase is quite something, connecting and syncing to hundreds of internal systems.

Needless to say estimates vs reality have been swinging wildly in all directions since forever. The processes, red tape, regulations and politics are consistently extreme so from software dev perspective its a very lengthy process while actual code changes take absolutely tiny time in whole project.

Re: How I estimate work

#140

After owning a product, I've developed a lot of sympathy for the people outside of engineering who have to put up with us. Engineers love to push back on estimates, believing that "when it's done" is somehow acceptable for the rest of the business to function. In a functioning org, there are lot of professionals depending on correct estimation to do their job. For us, an accurate delivery date on a 6 month project wa…

I think the hardest part of estimation often gets glossed over: genuine technical unknowns. Not "we didn’t think hard enough," but cases where the work itself is exploratory.