Re: How I estimate work

#111

After owning a product, I've developed a lot of sympathy for the people outside of engineering who have to put up with us. Engineers love to push back on estimates, believing that "when it's done" is somehow acceptable for the rest of the business to function. In a functioning org, there are lot of professionals depending on correct estimation to do their job. For us, an accurate delivery date on a 6 month project wa…

This is true, but the problem is that engineers are being asked to over-extrapolate given the evidence, and expected to own that extrapolation despite the paucity of evidence to make a good estimate. I *HATE* estimating roadmaps, because it feels unfair. I'm happy to estimate a sprint.

Yes. I took over the project management of a job where the previous project manager had spent a year planning it out, but development had not yet started. The client was furious, understandably.

I abandoned the plans from the previous PM and discussed the job with the developer who ballpark estimated that the work would take 2 months. After a quick analysis I adjusted this to 14 weeks.

But the account manager thought this sounded too long and insisted that we plug everything in to a Gantt chart, define the shit out of everything, map the dependencies, etc, which showed that the development would only take 6 weeks.

The project ended up taking 14 weeks.

Re: How I estimate work

#112
post #63

After owning a product, I've developed a lot of sympathy for the people outside of engineering who have to put up with us. Engineers love to push back on estimates, believing that "when it's done" is somehow acceptable for the rest of the business to function. In a functioning org, there are lot of professionals depending on correct estimation to do their job. For us, an accurate delivery date on a 6 month project wa…

I used to work in the semiconductor industry writing internal tools for the company. Hardware very rarely missed a deadline and software was run the same way. Things rarely went to plan, but as soon as any blip occured, there'd be plans to trim scope, crunch more, or push the date with many months of notice. Then I joined my first web SaaS startup and I think we didn't hit a single deadline in the entire time I worke…

What was the thing you were estimating? R&D?

I think you were estimating time to build things that were out of R&D and you had specifications that were actual specifications you were building up to.

In SaaS my experience is: someone makes up an idea not having any clue how existing software is working or is laid out, has no specifications beside vague not organized bunch of sentences. Software development team basically starts R&D to find out specifications and what is possible - but is expected to deliver final product.

Re: How I estimate work

#114
post #69

After owning a product, I've developed a lot of sympathy for the people outside of engineering who have to put up with us. Engineers love to push back on estimates, believing that "when it's done" is somehow acceptable for the rest of the business to function. In a functioning org, there are lot of professionals depending on correct estimation to do their job. For us, an accurate delivery date on a 6 month project wa…

> Trim features, push date, bring in extra help, or crunch. There are problems with all of these. The company knows they can sell X of the product for $Y (often X is a bad guess, but sometimes it has statistical range - I'll ignore this for space reasons but it is important!). X times Y equals gross profit. If the total costs to make the feature are too high the whole shouldn't be done. If you trim features - the aff…

They don't NEED them, but better project estimates can reduce the error bars on other dependent estimates (e.g. estimated sales, estimated ship dates, estimated staffing requirements, etc...), and that might be useful to a business (or not).

Re: How I estimate work

#115
A lot of this felt very familiar. Having multiple plans does seem like a good way to hedge against the unknown, but I can also see that you'd end up with the "secret 5th" plan when all of those unknowns eventually stack up.

Planning is inaccurate, frustrating, and sadly necessary.

Re: How I estimate work

#116
post #69

After owning a product, I've developed a lot of sympathy for the people outside of engineering who have to put up with us. Engineers love to push back on estimates, believing that "when it's done" is somehow acceptable for the rest of the business to function. In a functioning org, there are lot of professionals depending on correct estimation to do their job. For us, an accurate delivery date on a 6 month project wa…

> Trim features, push date, bring in extra help, or crunch. There are problems with all of these. The company knows they can sell X of the product for $Y (often X is a bad guess, but sometimes it has statistical range - I'll ignore this for space reasons but it is important!). X times Y equals gross profit. If the total costs to make the feature are too high the whole shouldn't be done. If you trim features - the aff…

If your business model needs the impossible then it's a bad business model. If your margins are too thin to absorb the schedule uncertainty then don't produce software.

Alternatively treat it like a bet and accept it may not pay off, just like any other business where uncertainty is the norm (movies, books, music).

Re: How I estimate work

#117

After owning a product, I've developed a lot of sympathy for the people outside of engineering who have to put up with us. Engineers love to push back on estimates, believing that "when it's done" is somehow acceptable for the rest of the business to function. In a functioning org, there are lot of professionals depending on correct estimation to do their job. For us, an accurate delivery date on a 6 month project wa…

I agree. Software engineering is basically the only industry that pretends this is professionally acceptable. Imagine if government staff asked when a bridge would be done or how much it would cost and the lead engineer just said "it's impossible to estimate accurately, so we wont. It's a big project tho". Estimating in software is very hard, but that's not a good reason to give up on getting better at it

Ever heard of Big Dig in Boston, for example? Or the Joint Strike Fighter?

Estimations in government contracts are as ridiculous as in software. They just pretend to be able to estimate when things will be done, when, in fact, the contractors are as clueless.

Not being able to say "it is impossible to estimate", does not mean your estimate will be correct. That estimation is usually a lie.

Re: How I estimate work

#118

Earlier quoted context omitted.

I'm a dev, not a salesperson, but let's be realistic. A company tells you "yeah we're interested in signing at $1M/yr, but we really need this feature, when will you have it by?", to which saying "eh we don't know - it'll be done when it's done" will lead to the company saying "ok well reach out when you have it, we can talk again then" (or just "eh ok then not a good fit sorry bye"), and in the meantime they'll go s…

Just to consider the opposite viewpoint, I sometimes wonder if it's not better that they do churn in that case. Assuming the sales team is doing their job properly, there are other prospects who may not need that feature, and not ramming the feature in under time constraints will lead to a much better product. Eventually, their feature will be built, and it will have taken the time that it needed, so they'll probably…

I understand the intuition, but it's a misunderstanding of how software sales operates. There's no tradeoff between prospects who need new features and prospects who don't, because salespeople love that second category and you'll have no problem hiring as many as you need to handle all of them.

Re: How I estimate work

#119
post #96
post #81

Earlier quoted context omitted.

Not a good analogy. Once you build a bridge, it’s done. Software nowadays is never “done”, and requirements constantly change. It’s more akin to building a rope bridge and trying to upgrade it to accommodate cars while it’s in active use.

Sounds like you don't have a good process for handling scope changes. I should know, the place I'm at now it's lacklustre and it makes the job a lot harder. Usually management backs off if they have a good understanding of the impact a change will make. I can only give a good estimate of impact if I have a solid grip on the current scope of work and deadlines. I've found management to be super reasonable when they ac…

I feel like some people in this thread are talking about estimates and some are talking about deadlines. Of course we should be able to give estimates. No, they're probably not very accurate. In many industries it makes sense to do whatever necessary to meet the estimate which has become a deadline. While we could do that in software, there often isn't any ramifications of going a bit overtime and producing much more value. Obviously this doesn't apply to all software. Like gamedev, especially before digital distribution.

I think it's obvious that all software teams do some kind of estimates, because it's needed for prioritization. Giving out exact dates as estimates/deadlines is often completely unecessary.