Re: How I estimate work

#61

After owning a product, I've developed a lot of sympathy for the people outside of engineering who have to put up with us. Engineers love to push back on estimates, believing that "when it's done" is somehow acceptable for the rest of the business to function. In a functioning org, there are lot of professionals depending on correct estimation to do their job. For us, an accurate delivery date on a 6 month project wa…

You're saying it would be convenient for you to know the future. It would also be convenient for me. That said, if you haven't done very similar work in the past, it's very unlikely you'll know exactly how much time it will take.

In practice developers have to "handle" the people requesting hard deadlines. Introduce padding into the estimate to account for the unexpected. Be very specific about milestones to avoid expectation of the impossible. Communicate missed milestones proactively, and there will be missed milestones. You're given a date to feel safe. And sometimes you'll cause unnecessary crunch in order for a deadline you fought for to be met. Other times, you'll need to negotiate what to drop.

But an accurate breakdown of a project amounts to executing that project. Everything else is approximation and prone to error.

Re: How I estimate work

#62

Features : Quality : Timeline Choose 2. For example a large feature set can be made quickly, but it will be of poor quality. Note that cost is somewhat orthogonal, throwing money at a problem does not necessarily improve the tradeoff, indeed sometimes it can make things worse.

Agree. I feel people with less clarity about priorities of features waste too much time by asking accurate estimates

Re: How I estimate work

#63

After owning a product, I've developed a lot of sympathy for the people outside of engineering who have to put up with us. Engineers love to push back on estimates, believing that "when it's done" is somehow acceptable for the rest of the business to function. In a functioning org, there are lot of professionals depending on correct estimation to do their job. For us, an accurate delivery date on a 6 month project wa…

I used to work in the semiconductor industry writing internal tools for the company. Hardware very rarely missed a deadline and software was run the same way.

Things rarely went to plan, but as soon as any blip occured, there'd be plans to trim scope, crunch more, or push the date with many months of notice.

Then I joined my first web SaaS startup and I think we didn't hit a single deadline in the entire time I worked there. Everyone thought that was fine and normal. Interestingly enough, I'm not convinced that's why we failed, but it was a huge culture shock.

Re: How I estimate work

#64
Article resonates with me. This time around, we asked cursor to estimate giving PRD & codebase. It gave very detailed estimate. Currently in the process of getting it down to what leadership wants (as in the article). AI estimates much better & faster than us. We are bringing it down much faster than AI. Sometimes changing the PRD or prioritizing the flows & cutting down scope of MVP. Honestly AI is a great tool for estimation.

Re: How I estimate work

#65
post #23

Estimation is an art, not a science. It's always going to be a judgement call by the engineers tasked with giving them to management. Taking all of the factors from this article and beyond can and should go into making that judgement call. I always tell my teams just skip the middlemen and think of estimates as time from the jump. It's just easier that way. As soon as an estimate leaves an engineer's mouth, it is eag…

You can improve if you follow up the estimates. My team had several months when we were within +- 10% in the aggregate.

I second this. If you don't close the loop, if you don't keep track of what you estimated and how long it took, how are your estimates going to get better? They aren't.

Is that a problem? Well, how good are they now?

Re: How I estimate work

#66

The most important part of the article is ”I gather as much political context as possible before I even look at the code.”

Exactly. The principle to go by for estimates is finding a balance between time/scope/cost, and figuring out which aspects of the context affect which dimension is the first step.

Re: How I estimate work

#67
> This is, of course, false. As every experienced software engineer knows, it is not possible to accurately estimate software projects.

This is a cop-out. Just because you can’t do it, doesn’t mean it’s impossible :)

There are many types of research and prototyping project that are not strongly estimable, even just to p50.

But plenty can be estimated more accurately. If you are building a feature that’s similar to something you built before, then it’s very possible to give accurate estimates to, say, p80 or p90 granularity.

You just need to recognize that there is always some possibility of uncovering a bug or dependency issue or infra problem that delays you, and this uncertainty compounds over longer time horizon.

The author even gestures in this direction:

> sometimes you can accurately estimate software work, when that work is very well-understood and very small in scope. For instance, if I know it takes half an hour to deploy a service

So really what we should take from this is that the author is capable of estimating hours-long tasks reliably. theptip reports being able to reliably estimate weeks-long tasks. And theptip has worked with rare engineers who can somehow, magically, deliver an Eng-year of effort across multiple team members within 10% of budget.

So rather than claim it’s impossible, perhaps a better claim is that it’s a very hard skill, and pretty rare?

(IMO also it requires quite a lot of time investment, and that’s not always valuable, eg startups usually aren’t willing to implement the heavyweight process/rituals required to be accurate.)

Re: How I estimate work

#68

After owning a product, I've developed a lot of sympathy for the people outside of engineering who have to put up with us. Engineers love to push back on estimates, believing that "when it's done" is somehow acceptable for the rest of the business to function. In a functioning org, there are lot of professionals depending on correct estimation to do their job. For us, an accurate delivery date on a 6 month project wa…

I agree. Software engineering is basically the only industry that pretends this is professionally acceptable. Imagine if government staff asked when a bridge would be done or how much it would cost and the lead engineer just said "it's impossible to estimate accurately, so we wont. It's a big project tho".

Estimating in software is very hard, but that's not a good reason to give up on getting better at it

Re: How I estimate work

#69

After owning a product, I've developed a lot of sympathy for the people outside of engineering who have to put up with us. Engineers love to push back on estimates, believing that "when it's done" is somehow acceptable for the rest of the business to function. In a functioning org, there are lot of professionals depending on correct estimation to do their job. For us, an accurate delivery date on a 6 month project wa…

> Trim features, push date, bring in extra help, or crunch.

There are problems with all of these. The company knows they can sell X of the product for $Y (often X is a bad guess, but sometimes it has statistical range - I'll ignore this for space reasons but it is important!). X times Y equals gross profit. If the total costs to make the feature are too high the whole shouldn't be done.

If you trim features - the affects either the number you can sell, or the price you can sell for (sometimes both).

If you push the date that also affects things - some will buy from a competitor (if possible - and the later date makes it more likely the competitors releases with that feature).

Bring in extra help means the total costs goes up. And worse if you bring them in too late that will slow down the delivery.

Crunch is easiest - but that burns out your people and so is often a bad answer long term.

This is why COMPANIES NEED ACCURATE ESTIMATES. They are not optional to running a company. That they are impossible does not change the need. We pretend they are possible because you cannot run a company without - and mostly we get by. However they are a fundamental requirement.

Re: How I estimate work

#70
Compare this with how customer requests end up in products in startups:

Step 1: Customer Sales/Product (i.e., CEO). Step 2: Product Direct to Engineering (i.e., CTO)

The latency between Step1 and Step2 is 10 minutes. CEO leaves the meeting takes a piss and calls the CTO.

- Simple features take a day: CTO to actual implementation latency depends on how hands on the CTO is. In good startups CTO is the coder. Most features will make its way into the product in days.

- Complex Features take a few days: This is a tug of war between CTO - CEO and indirectly the customer. CTO will push back and try to hit a balance with CEO while the CEO works with the customer to find out what is acceptable. Again latency is measured by days.

Big companies cannot do this and will stifle your growth as an engineer. Get out there and challenge yourselves.