Spain is mostly back up. Plant startup is only the first step.[1] It's load pickup. Here is a PJM training module on load pickup during system restoration.[2] It gives a sense of how touchy the process is. Power network control has good control over generation and transmission, but limited control over load. When load is turned on, there are transient loads with different time constants. There's a huge load for the f…
The groundwork for the blackout will inevitably come back to a buildout and reliance of renewable sources that do not have spinning mass that can do frequency synchronization. There are costly means to compensate for the lack of spinning baseload but actually building these devices have been neglected, to no ones surprise.
Looking at power generation reports it's the plants relying on inertia (like nuclear) which were disconnected and haven't been reconnected since: