The obligatory "what's the capacity factor" discussion should happen here; 40% to 50% might be reasonable, with highly correlated availability. Additionally the wind farm requires backup (CCGT or OCGT), which cost money to sit there. https://assets.publishing.service.gov.uk/media/6556027d046ed... (take it with a pinch of salt) gives a figure of £80/kW/year for an H class CCGT; that's £250M/year (2015 prices). Another…
The capex per watt of gas backup is vastly lower than a nuclear plant. Like, by a factor of 10 to 20.
https://www.iea.org/reports/projected-costs-of-generating-el... tables Table 3.2a and 3.4a show that Korean CCGT cost 838 USD/kWe and Korean PWRs were 2157 USD/kWhe (all 2018 prices).
Anyhow, gas backup fuel costs (and carbon taxes) are where the real big costs are.