What exactly is it Bechtel and friends struggling with?Some of it is reasonable. Covid threw a spanner in schedules and increased costs due to a rise in price levels. Some is from design changes due to new information, e.g. "during launch, the SLS generates exhaust blast plume pressure, random vibration, vibration from acoustics, and heat. These loads can cause damage to the launch vehicle, payload, launch pad, and surrounding structures. After the Artemis I launch, NASA found higher-than-expected thermal, acoustic, and blast loads to the ML-1. ML-2 project
management is assessing these lessons learned from Artemis I and anticipates the ML-2 structure will require some additional strengthening to withstand the predicted loads" [1].
A lot of it, however, is laughably-incompetent cost-plus subcontracting nonsense:
"While Bechtel revised its IFCs in response to the RFIs, according to ML-2 project management, the
company did not allot sufficient time in its schedule to do so, and this iterative process resulted in cost increases and schedule delays. In mid-2023, ML-2 project management found the delays in steel fabrication and delivery resulted in a 3-month schedule slip, leaving Bechtel with no additional schedule reserve to meet the May 2026 contract end date.
...
In mid-2021, ML-2 project management noted that Bechtel’s 'interactions and business relationship with the steel fabricator deteriorated to the point of dysfunction,' resulting in unresolved fabrication issues that impacted the ML-2 project’s critical path. Bechtel’s lack of awareness and oversight of critical second-tier subcontractors responsible for steel fabrication contributed to a delayed construction start date. One subcontractor, which Bechtel allocated approximately 46 percent of the fabrication work to, sold all of its shop space to a non-NASA customer because Bechtel's steel fabrication plan lacked a signed contract with the subcontractor. As a result, Bechtel attempted to find another subcontractor with available shop space but was unable to do so in a timely manner. The delay in the steel fabrication process continued to impact the ML-2 project’s schedule" (pp 18).
[1] https://oig.nasa.gov/wp-content/uploads/2024/08/ig-24-016.pd... page 20