Re: Story points are pointless, measure queues

#81

Story points aren't time (as OP states). They're relative complexity, and uncertainty (hence the fibbonacci sequence building uncertainty in to larger numbers). And stories should be able to sized as big numbers. I've never been on a team comfortable with more than a 7, at least not since my first agile experience where we all took an agile/scrum training together for a few days. We'd frequently give things like 21 o…

> Story points aren't time...

> ...burndown chart...

The x-axis of a burndown chart is time, right? So if you create a chart that measures points/time then you encourage the idea that a certain number of points can/should be completed in a day, ergo that points are a proxy for units of time. Otherwise what's the point in the chart?

Re: Story points are pointless, measure queues

#82
post #10

Earlier quoted context omitted.

I agree - just countless times I have to beat that up into peoples head and even people who I would consider smart "points time". After the sprint you can kind of infer the time but it should not be guideline for next estimations unless these are tasks like "fix typos".

If they're not time, why use numbers? Use fruits: easy peasy, it's a lemon. A really tough story, a coconut. You can't add them in any case, because they're not time.

Just because they're not time, doesn't mean you don't want to add them. Imagine you have an empty basket, and you're not sure how much fruit you can toss in it. So the first time, you just start tossing stuff in until it's full. The exact number of lemons, coconuts, etc will vary. But after a few rounds, you'll get a feel for how much of each you can get into the basket. That's story points. You feel your way into a groove where the team gets a more concrete sense about how much it can get done in a sprint, given the variability of the work, external projects/distractions, and the makeup of the team.

Story points get a bad rap because a lot of engineering managers don't get scrum and just see a convenient way to measure productivity. Which story points are absolutely not meant to do, outside of the team itself setting its own sprint goals.

Re: Story points are pointless, measure queues

#83

The fundamental issue isn't addressed but it sure is hinted at. Scheduling is an NP problem. As queue size, or backlog, or (insert thing here that tracks work to be done) grows it takes n^p calculations to schedule it optimally. This is hit on when it mentions small teams hitting their estimates. They can do this because their task list is small enough to go through all the permutations and actually come up with an a…

> Scheduling is an NP problem. [...] it takes n^p calculations to schedule it optimally That isn't what NP means. (An O(n^p) algorithm would in fact be in P.)

yep. I wrote without thinking. c^n would be better right.

Re: Story points are pointless, measure queues

#84

My personal experience with story points is that the number never really mattered, but the process of the team discussing how to rate the complexity of a task was very useful. In terms of having utility of estimating how long something will take, I personally have never been able to translate story points into a reliable indicator for that for many reasons (e.g team changing, domain changing, variability in operation…

Software does not exist in a vacuum. You are probably right in thinking that story points should not matter to you, as a developer; but they do matter to external stakeholders.

Forecasting and management of expectations is necessary because software often has external real-world dependencies: available funding for a first release, marketing materials, hardware that can't be released without software, trade shows, developer conferences, yearly retail release parties, OEM partners, cyclic stable releases for enterprise customers who won't push software into production without extensive pre-testing, graphics adapters that can't be released without drivers, rockets that won't launch, cars that won't drive, etc.

All of these things require some degree of forecasting and appropriately-evolving management of expectations. Here's where we stand. Here's what we can commit to. Here's what we might deliver, but are willing to defer to a future release. Here are the (low value) items were under consideration that we will definitely defer to a future release, here are the features you will need to drop to get feature b in this release.

The purpose of story points is to help provide forecasting and management of expectations (with appropriately limited commitments) to stakeholders, on the understanding that forecasts are approximate.

Calibrated burndown of story points is pretty much the only basis on which forecasting and management of expectations can be done in an agile process. The key is to make sure that stakeholders understand the difference between forecasting and commitment, and to make sure your development team is appropriately protected by a healthy development process.

Whether the author's claim that you get better forecasts by just counting stories, instead of summing story points... color me skeptical. I do get that it prevents some obvious abuses of process, while enabling other that are just as bad. If somebody is using story points as a developer performance metric (which they shouldn't), there's nothing that prevents them from using completed stories as a developer performance metric (which they shouldn't). The corresponding abuse of process to combat that metric would be to hyper-decompose stories.

Re: Story points are pointless, measure queues

#87
Just estimate time. In the end, whenever I worked with story points in various companies, even though developers, Project Managers or Scrum Masters would often state that Story Points are a measure of complexity, in the end, the Velocity for a given sprint was measured in Story Points as well. So, in the end a Story Point is equal to an amount of time in a sprint.

This is also stated in the article:

> Story points do not represent Time, yet the Velocity metric they are usually combined with defacto converts them to time, sabotaging everyone from the start by doing the thing that you can't do with a precise number and a range...adding them together.

Better yet, just don't bother with SCRUM and all it's pointless and time-consuming ceremonies and just get shit done. This is my preferred mode of working and I've been lucky to be able to work like this for the last couple of years.

Re: Story points are pointless, measure queues

#88
post #10

Earlier quoted context omitted.

I agree - just countless times I have to beat that up into peoples head and even people who I would consider smart "points time". After the sprint you can kind of infer the time but it should not be guideline for next estimations unless these are tasks like "fix typos".

Ultimately, we are bound by time, not complexity. Why does it matter how complex a task is? The product managers and customers wont care how hard we as engineers have to think or reason about a problem; to them, the only thing that matters is time until delivery.

Points are about uncertainty, they're the difference between:

- 3-4 weeks

- 3-9 weeks

Product managers can get their head around that.

Re: Story points are pointless, measure queues

#89

My personal experience with story points is that the number never really mattered, but the process of the team discussing how to rate the complexity of a task was very useful. In terms of having utility of estimating how long something will take, I personally have never been able to translate story points into a reliable indicator for that for many reasons (e.g team changing, domain changing, variability in operation…

>In terms of having utility of estimating how long something will take, I personally have never been able to translate story points into a reliable indicator for that for many reasons (e.g team changing, domain changing, variability in operational load outside of development work). If your measure of the utility of story points is how well they help you estimate time, then you're right, they're useless to you. If you…

>back-of-the-envelope way to estimate which bits of validated functionality you're going to be able to get into the codebase this sprint

>help you estimate time

How are these different?

Re: Story points are pointless, measure queues

#90
post #87

Just estimate time. In the end, whenever I worked with story points in various companies, even though developers, Project Managers or Scrum Masters would often state that Story Points are a measure of complexity, in the end, the Velocity for a given sprint was measured in Story Points as well. So, in the end a Story Point is equal to an amount of time in a sprint. This is also stated in the article: > Story points do…

I disagree with the first part. The only thing less useful than estimating points is estimating hours.