https://twitter.com/olesovhcom/status/1369504527544705025 "Update 5:20pm. Everybody is safe. Fire destroyed SBG2. A part of SBG1 is destroyed. Firefighters are protecting SBG3. no impact SBG4."
“SBG1, the first Strasbourg data center, consisting of twelve containers, came online in 2012. The 12 containers had a capacity of 12,000 servers.
SBG2 is a non-container data center in 2016 using its “Tower” design with a capacity of 30,000 servers.
SBG3 tower was built in 2017 with a capacity of 30,000 servers.
SBG4 was built in 2013 as several containers to augment capacity, but was decommissioned in 2018 and moved to SB3”