I'm not sure if you agree that the findings are unsustainable or not. Two things that the IAEA had established were that
1) Fukishima survived the earthquake as designed, and was in the process of shutting down when the tsunami hit.
2) The tsunami disabled primary and backup power to the cooling systems which was the proximate cause of the failure.
Further, at the time of its commissioning, the tsunami it experienced was accepted by the best engineering data at the time to be impossible.
You can make the argument that over time as more data became available the regulatory agency should have required additional upgrades to cover the larger tsunami risk. There have been plenty of stories about regulatory capture between TEPCO and the regulators which prevented best practices from being followed.
A lot of retrofits had been installed over time and that no doubt contributed to its survival of the earthquake.