Ask HN: Is there academic research on the effectiveness of estimation in scrum?
1–7 of 7 posts
Re: Ask HN: Is there academic research on the effectiveness of estimation in scrum?
#2This person has done some stuff on some aspects: https://collaboration.csc.ncsu.edu/laurie/publicationsAll.ht...
Re: Ask HN: Is there academic research on the effectiveness of estimation in scrum?
#3Since you need multiple teams, building similar software in order to compare.
Re: Ask HN: Is there academic research on the effectiveness of estimation in scrum?
#4"The most surprising part of the 1985 Jeffery-Lawrence study appeared at the very end, when they investigated the productivity of 24 projects for which no estimates were prepared at all. These projects far outperformed all the others (see Table 5-3)."
Table 5-3 Productivity by Estimation Approach (Full Result)
-----------------------------------------------------------------------
Effort Estimate Prepared by Average Productivity Number of Projects
-----------------------------------------------------------------------
Programmer alone 8.0 19
Supervisor alone 6.6 23
Promgrammer & supervisor 7.8 16
System analyst 9.5 21
(no estimate) 12.0 24
Source: https://www.amazon.com/Peopleware-Productive-Projects-Teams-...Re: Ask HN: Is there academic research on the effectiveness of estimation in scrum?
#5Not specific to scrum but I am reminded of a part from Peopleware: "The most surprising part of the 1985 Jeffery-Lawrence study appeared at the very end, when they investigated the productivity of 24 projects for which no estimates were prepared at all. These projects far outperformed all the others (see Table 5-3)." Table 5-3 Productivity by Estimation Approach (Full Result) -----------------------------------------…
Re: Ask HN: Is there academic research on the effectiveness of estimation in scrum?
#6Re: Ask HN: Is there academic research on the effectiveness of estimation in scrum?
#7https://www.iancarroll.com/2016/04/18/no-correlation-between...