Re: Building the heap: racking 30 petabytes of hard drives for pretraining

#61
post #48

Earlier quoted context omitted.

So the drives are never going to fail? PSUs are never going to burn out? You are never going to need to procure new parts? Negotiate with vendors?

This concern troll that everyone trots out when anyone brings up running their own gear is just exhausting. The hyperscalers have melted people’s brains to a point where they can’t even fathom running shit for themselves. Yes, drives are going to fail. Yes, power supplies are going to burn out. Yes, god, you’re going to get new parts. Yes, you will have to actually talk to vendors. Big. Deal. This shit is -not- hard.…

Very good point. There was something on the HN front page like this about self-hosted email, too.

I point out to people that AWS is between ten to one hundred times more expensive than a normal server. The response is "but what if I only need it to handle peak load three hours a day?" Then you still come out ahead with your own server.

We have multiple colo cages. We handle enough traffic - terabytes per second - that we'll never move those to cloud. Yet management always wants more cloud. While simultaneously complaining about how we're not making enough money.

Re: Building the heap: racking 30 petabytes of hard drives for pretraining

#62
post #38

Is it correct that you have zero data redundancy? This may work for you if you're just hoarding videos from YouTube, but not for most people who require an assurance that their data is safe. Even for you, it may hurt proper benchmarking, reproducibility, and multi-iteration training if the parent source disappears.

Definitely much less redundancy, this was definitely a tradeoff we made for pretraining data and cost.

Did you do any kind of redundancy at least (eg: putting every 10 disks in RAID 5 or RAID Z1)? Or I suppose your training application doesn't mind if you shed a few terabytes of data every so often?

Re: Building the heap: racking 30 petabytes of hard drives for pretraining

#65

The biggest part that is always missing in such comparisons is the employee salaries. In the calculation they give $354k/year of total cost per year. But now add the cost of staff in SF to operate that thing.

Small startup teams can sometimes get away with datacenter management being a side task that gets done on an as-needed basis at first. It will come with downtime and your stability won't be anywhere near as good as Cloudflare or AWS no matter how well you plan, though.

Every real-world colocation or self-hosting project I've ever been around has underestimate their downtime and rate of problems by at least an order of magnitude. The amount of time lost to driving to the datacenter, waiting for replacement parts to arrive, and scrambling to patch over unexpected failure modes is always much higher than expected.

There is a false sense of security that comes in the early days of the project when you think you've gotten past the big issues and developed a system that's reliable enough. The real test is always 1-2 years later when teams have churned, systems have grown, and the initial enthusiasm for playing with hardware has given way to deep groans whenever the team has to draw straws to see who gets to debug the self-hosted server setup this time or, worse, drive to the datacenter again.

Re: Building the heap: racking 30 petabytes of hard drives for pretraining

#66
post #13

Used Disks, No DR, not exactly a real shoot out.

True, though this is specifically for pretraining data (S3 wouldn't sell us used disk + no DR storage).

I do appreciate the scrappiness of your solution. Used drives for a storage cluster is like /r/homelab on steroids. And since it's pretraining data, I suppose data integrity isn't critical.

Most venture-backed startups would have just paid the AWS or Cloudflare tax. I certainly hope your VCs appreciate how efficient you are being with their capital :)

Re: Building the heap: racking 30 petabytes of hard drives for pretraining

#67
post #60

The biggest part that is always missing in such comparisons is the employee salaries. In the calculation they give $354k/year of total cost per year. But now add the cost of staff in SF to operate that thing.

The biggest part missing from the opposing side is: Their view is very much rooted in the pre-Cloud hardware infrastructure world, where you'd pay sysadmins a full salary to sit in a dark room to monitor these servers. The reality nowadays is: the on-prem staff is covered in the colo fees, which is split between everyone coloing in the location and reasonably affordable. The software-level work above that has massive…

> do you think managing IAM and Terraform is free?

No, but I would argue that a SaaS offering, where the whole maintenance of the storage system is maintained for you actually requires less maintenance hours than hosting 30 PB in a colo.

In terraform you define the S3 bucket and run terraform apply. Afterwards the company's credit card is the limit. Setting up and operating 30 PB yourself is an entirely different story.

Re: Building the heap: racking 30 petabytes of hard drives for pretraining

#69
post #45

It's quite cheap to just store data at rest, but I'm pretty confused by the training and networking set up here. It sounds like from other comments that you're not going to put the GPUs in the same location, so you'll be doing all training over X 100 Gbps lines between sites? Aren't you going to end up totally bottlenecked during pretraining here?

yeah we just have the 100gig link, atm that's about all the gpu clusters can pull but we'll prob expand bandwidth and storage as we scale.

I guess worth noting that we do have a bunch of 4090s in the colo and it's been super helpful for e.g. calculating embeddings and such for data splits.

Re: Building the heap: racking 30 petabytes of hard drives for pretraining

#70

The biggest part that is always missing in such comparisons is the employee salaries. In the calculation they give $354k/year of total cost per year. But now add the cost of staff in SF to operate that thing.

Small startup teams can sometimes get away with datacenter management being a side task that gets done on an as-needed basis at first. It will come with downtime and your stability won't be anywhere near as good as Cloudflare or AWS no matter how well you plan, though. Every real-world colocation or self-hosting project I've ever been around has underestimate their downtime and rate of problems by at least an order o…

> The amount of time lost to driving to the datacenter, waiting for replacement parts to arrive, and scrambling to patch over unexpected failure modes is always much higher than expected.

I don't have this experience at all. Our colo handled almost all work. the only time i ever went to the server farm was to build out whole new racks. Even replacing servers the colo handled for us at good cost.

Our reliability came from software not hardware, though of course we had hundreds of spares sitting by, the defense in depth (multiple datacenters, each datacenter having 2 'brains' which could hotswap, each client multiply backed up on 3-4 machines)...

servers going down were fairly common place, servers dying were commonplace. i think once we had a whole rack outage when the switch died, and we flipped it to the backup.

Yes these things can be done and a lot cheaper than paying AWS.