You can put up a plant in 5 years without erroneous regulation.
Do you have some examples of that in the last decades?
https://en.wikipedia.org/wiki/Barakah_nuclear_power_plant
Nameplate capacity 5600 MW
Construction began
Unit 1: 19 July 2012
Unit 2: 16 April 2013
Unit 3: 24 September 2014
Unit 4: 30 July 2015
Commission date
Unit 1: 3 August 2020
Unit 2: 14 September 2021
Unit 3: 10 October 2022
Unit 4: 23 March 2024