So this may not be fair, but you lost me quite a bit with the positive take on SAFe, which is the worst, most unproductive experience of any process I’ve had. I also do not understand the queues and capacity issue. I have never been in an environment where we do not have so much work that we cannot meaningfully see past the end of the queue. I don’t necessarily view that as a bad thing.
Alright, comment part 2 since I have a little more time now. First, the SAFe explanation. I've been a software developer for a little over 22 years. My first experience managing a team was 12 years ago and I shifted to it full time in 2018. My entire motivation for doing this was living through environments that were painful and unproductive for everyone involved. I found Reinertsen during a lot of reading when I was…
My experience was that maybe 20-40 percent of the plan ended up working (blocked by external factors, shifting market landscape, missed or unexpected work coming up), and then there was a huge amount replanning and time wasted.
I just cannot reconcile that 8-12 week cycles is in any way conducive to agile development.