From today’s Orbital Index ( https://orbitalindex.com/archive/2020-01-30-Issue-49/ ): The Best Way to Make a Profit as an Aerospace Company is to Fail ( https://qz.com/1784335/the-space-military-industrial-complex... ), a compelling piece about how massive corporations like Northrop Grumman have little incentive to hit their contract budgets and are arguably incentivized not to. “Northrop Grumman […] won the James We…
I never understood why there aren't performance requirements in government contracts. Same thing with infrastructure construction here in DC... new offices go up in a year, but changes to the intersection in front of said office take 5 years and cost multiple of the office itself. [hyperbole, but only just]
Boeing reports a $410M charge in case NASA decides Starliner needs another test
21–30 of 58 posts
Re: Boeing reports a $410M charge in case NASA decides Starliner needs another test
#22Earlier quoted context omitted.
I never understood why there aren't performance requirements in government contracts. Same thing with infrastructure construction here in DC... new offices go up in a year, but changes to the intersection in front of said office take 5 years and cost multiple of the office itself. [hyperbole, but only just]
I'm starting to believe it'd be cheaper to just start out the same project with 2 or 3 companies, and then just keep the be st performing one and dump the other two as soon as its clear that one will be finishing the project in time and within budget. That would only double the cost (if you dump early enough) of a govt project, and since most projects seem to have a budget overrun much larger than that, it'd actually…
Re: Boeing reports a $410M charge in case NASA decides Starliner needs another test
#23From today’s Orbital Index ( https://orbitalindex.com/archive/2020-01-30-Issue-49/ ): The Best Way to Make a Profit as an Aerospace Company is to Fail ( https://qz.com/1784335/the-space-military-industrial-complex... ), a compelling piece about how massive corporations like Northrop Grumman have little incentive to hit their contract budgets and are arguably incentivized not to. “Northrop Grumman […] won the James We…
Re: Boeing reports a $410M charge in case NASA decides Starliner needs another test
#24Earlier quoted context omitted.
I never understood why there aren't performance requirements in government contracts. Same thing with infrastructure construction here in DC... new offices go up in a year, but changes to the intersection in front of said office take 5 years and cost multiple of the office itself. [hyperbole, but only just]
I'm starting to believe it'd be cheaper to just start out the same project with 2 or 3 companies, and then just keep the be st performing one and dump the other two as soon as its clear that one will be finishing the project in time and within budget. That would only double the cost (if you dump early enough) of a govt project, and since most projects seem to have a budget overrun much larger than that, it'd actually…
Re: Boeing reports a $410M charge in case NASA decides Starliner needs another test
#25From today’s Orbital Index ( https://orbitalindex.com/archive/2020-01-30-Issue-49/ ): The Best Way to Make a Profit as an Aerospace Company is to Fail ( https://qz.com/1784335/the-space-military-industrial-complex... ), a compelling piece about how massive corporations like Northrop Grumman have little incentive to hit their contract budgets and are arguably incentivized not to. “Northrop Grumman […] won the James We…
Re: Boeing reports a $410M charge in case NASA decides Starliner needs another test
#26From today’s Orbital Index ( https://orbitalindex.com/archive/2020-01-30-Issue-49/ ): The Best Way to Make a Profit as an Aerospace Company is to Fail ( https://qz.com/1784335/the-space-military-industrial-complex... ), a compelling piece about how massive corporations like Northrop Grumman have little incentive to hit their contract budgets and are arguably incentivized not to. “Northrop Grumman […] won the James We…
Yes. It is great that NASA is trying to get away from this model with the Commercial Crew Program. Boeing would eat this cost, just like SpaceX does when it has problems. Cost plus contracts, while maybe necessary in some situations, evolves huge cost bloat in defense, large public works, and health insurance sectors of the economy.
Re: Boeing reports a $410M charge in case NASA decides Starliner needs another test
#27Earlier quoted context omitted.
There used to be a lot more defense contractors during the cold war. Also, more accountability. So there was competitive pressure to be seen as an organization that could reliably deliver projects. Over the years, many of the major companies merged, then shifted strategies to geographically dispersing their jobs to bolster congressional support. Take the Joint Strike Fighter / F-35 for example: 4 bids. Lockheed won t…
"There used to be a lot more defense contractors during the cold war. Also, more accountability. " Gear today is far more complicated. Schedule and cost increase geometrically with complexity. Many of the 'innovations' on early era fighters were quick iterations made by tiny teams. But it's no longer the 100's of fighters that will win, it's the one squadron with the best gear, radar, comms backed up by the rest of i…
Regardless of how complex or expensive a project it, if the people doing it aren't strongly incentivized (positively or negatively) to keep these things under control, the will not. That doesn't matter what era you are talking about.
Re: Boeing reports a $410M charge in case NASA decides Starliner needs another test
#28From today’s Orbital Index ( https://orbitalindex.com/archive/2020-01-30-Issue-49/ ): The Best Way to Make a Profit as an Aerospace Company is to Fail ( https://qz.com/1784335/the-space-military-industrial-complex... ), a compelling piece about how massive corporations like Northrop Grumman have little incentive to hit their contract budgets and are arguably incentivized not to. “Northrop Grumman […] won the James We…
I worked at Northrop Grumman a decade ago on a contract that was missing it's deadlines. It was pretty choatic, and management was not very good (every new thing became a #1 priority). To try to get things done we were allowed to work as much overtime as possible. They even had white board showing who had worked the most hours (the top several people people worked over 2000 extra hours during a 12 month period). I al…
11.5 hour days, 7 days a week for a year?
> I almost burned out
No kidding. Seems like a recipe for much worse than burn out.
Re: Boeing reports a $410M charge in case NASA decides Starliner needs another test
#29Earlier quoted context omitted.
I never understood why there aren't performance requirements in government contracts. Same thing with infrastructure construction here in DC... new offices go up in a year, but changes to the intersection in front of said office take 5 years and cost multiple of the office itself. [hyperbole, but only just]
I'm starting to believe it'd be cheaper to just start out the same project with 2 or 3 companies, and then just keep the be st performing one and dump the other two as soon as its clear that one will be finishing the project in time and within budget. That would only double the cost (if you dump early enough) of a govt project, and since most projects seem to have a budget overrun much larger than that, it'd actually…
Re: Boeing reports a $410M charge in case NASA decides Starliner needs another test
#30Earlier quoted context omitted.
I worked at Northrop Grumman a decade ago on a contract that was missing it's deadlines. It was pretty choatic, and management was not very good (every new thing became a #1 priority). To try to get things done we were allowed to work as much overtime as possible. They even had white board showing who had worked the most hours (the top several people people worked over 2000 extra hours during a 12 month period). I al…
> 2000 extra hours during a 12 month period 11.5 hour days, 7 days a week for a year? > I almost burned out No kidding. Seems like a recipe for much worse than burn out.