Is it really though? How many gigawatts of gas peaker plants and all the associated infrastructure sit around waiting for the tens or hundred hours they're needed?
Turns out, it's a lot - and it costs the ratepayers:
https://www.greentechmedia.com/articles/read/just-how-much-b...
> Wood Mackenzie calculates the average peaker plant capacity factor will sit between 5 and 6 percent over the next two decades. That amounts to a low number of hours for storage to replicate.
In New York City, ratepayers are paying billions of dollars for polluting gas peakers that sit idle.
https://www.cleanegroup.org/ceg-projects/phase-out-peakers/
* An estimated $4.5 billion in ratepayers funds have gone to support the continued operation of the city’s peaker plants – most of which operate no more than a few hundred hours each year.
* Even though the power plants don’t run often, they can be significant contributors to local air pollution – accounting for more than 10 percent of nitrous oxide (NOx) emissions on high ozone days.
Luckily we have the technology to both start replacing gas peakers with storage, and roll out demand response and load shedding to reduce peak demand.
For example, my employer is a big power user. On a couple days in the summer during peak heat, the utility requests curtailment. The plant managers can respond by switching HVAC operation plans, shift some loads to the overnight - the utility saves money on peak generation, and the company saves a ton of demand charges. Win-win.