Ask HN: Is there academic research on the effectiveness of estimation in scrum?

news.ycombinator.com

1–7 of 7 posts

Re: Ask HN: Is there academic research on the effectiveness of estimation in scrum?

#4
Not specific to scrum but I am reminded of a part from Peopleware:

"The most surprising part of the 1985 Jeffery-Lawrence study appeared at the very end, when they investigated the productivity of 24 projects for which no estimates were prepared at all. These projects far outperformed all the others (see Table 5-3)."

  Table 5-3 Productivity by Estimation Approach (Full Result)
  -----------------------------------------------------------------------
  Effort Estimate Prepared by   Average Productivity   Number of Projects
  -----------------------------------------------------------------------
  Programmer alone                     8.0                    19
  Supervisor alone                     6.6                    23
  Promgrammer & supervisor             7.8                    16
  System analyst                       9.5                    21
  (no estimate)                       12.0                    24
Source: https://www.amazon.com/Peopleware-Productive-Projects-Teams-...

Re: Ask HN: Is there academic research on the effectiveness of estimation in scrum?

#5

Not specific to scrum but I am reminded of a part from Peopleware: "The most surprising part of the 1985 Jeffery-Lawrence study appeared at the very end, when they investigated the productivity of 24 projects for which no estimates were prepared at all. These projects far outperformed all the others (see Table 5-3)." Table 5-3 Productivity by Estimation Approach (Full Result) -----------------------------------------…

This doesn't surprise me tbh. It's the same situation except you're not shackled by yesterday's commitments and free to act independently of them .

Re: Ask HN: Is there academic research on the effectiveness of estimation in scrum?

#6
Not scrum-specific, and I don't recall whether it was backed by academic research, but one of the rules in XP is that estimates longer than 3 weeks were (more) unreliable. So if the estimate was longer than 3 weeks, you had to break it up into chunks, each of which was 3 weeks or smaller.