It sounds like you're not delegating enough. This is key when you're managing, especially at a senior level. And not just technology-related stuff.

Pick two thresholds:

- Maximum amount of time you're willing to allocate to a specific task. (Example: 1h. FYI, David Allen of GTD fame recommends 5min for very senior execs.) Try to delegate anything above that number.

- Amount of time you'll take you to get it done vs amount of time it'll take one of your directs or skips to get something done. (Example: a task that you could do in 1h will require 10 man-hours if done downstream.) Pick a number and try to delegate anything that requires less downstream effort.

When it comes to delegating, remember: back when you were an engineer or a new manager, you sucked at what your boss was delegating to you, but you managed to produce something that was good enough and you became better at it with time. Your directs and your skips will learn too.

Also:

- Learn how to hire. If you're managing managers you absolutely want dependable directs who you trust will get done whatever stuff you delegate to them. And frankly, the same holds when you're managing engineers. (As an aside, a common mistake in early stage startups is to let the founders or HR hire for you; you're going to be the one managing whoever gets hired, so push back if you've no say over who gets hired.)

- Put a weekly 30min 1:1 with all of your directs in your calendar if you're not doing so already. It'll save you lots of interruptions because your directs will know they've some time allocated for less urgent stuff, and it'll allow you to surface incoming problems before they blow up in your face.

- Ax the time you spend on email to free up your calendar. Pick 2 or 3 time slots during your day. (Example: early morning upon arriving, before or after lunch, and before leaving.) Block those slots in your calendar. Only do email during those time slots. (Close your Email client and turn off notifications. If anything's actually urgent, your phone will ring.) Also, create filters to surface what's important and what's not. (Anything cc'd to you or not sent to your email directly probably isn't high priority; stuff sent by your boss or by your directs probably is.)

- Block a few hours in your calendar to actually get your own work done. Part of your job arguably is to be available, but if your calendar is wide open it invites your coworkers to swamp you with meetings. And be picky with meetings. Unless it's coming from your boss, refuse to join meetings that don't have a clear agenda. (Send one of your directs instead.)

- Build good-will and political capital in your organization. At senior levels, I'll scratch your back if you scratch mine tends to count a lot. So don't hesitate to spend a half hour every so often with other managers that deal with stuff your teams have interaction with to catch up. (There's no point in building a new product if the heads of marketing and sales don't both think there's a market.) Don't confuse this with schmoozing, else your weekly or fortnightly meeting will be first to get binned when calendar time is scarce. But work on those relationships.

Re: Ask HN: IT Directors and VP's – how do you manage your time and projects?

#22
My job changed from doing all the things to (a) picking which things should be done and (b) making sure that all those things get done.

We use a ticketing system that enforces a minimum amount of process and otherwise stays out of our way (RequestTracker, highly recommended). I keep the master project list in a text file. We have a weekly status meeting where the master project list is 80% of the agenda. The meeting usually lasts about 30 minutes unless we have something particularly deep to discuss, design or dispute.

We keep in close contact with our chat system, email, and in-person meetings when people feel like they need them.

Every morning I review:

- tickets generated by alerts. Did they get handled properly?

- new tickets from users. Have they been picked up?

- master project list. Does anything need my expertise?

Throughout the day I look for signs that I should help people with their tickets or projects. Occasionally that means solving the problem for them, but usually it means pointing them to the right documentation or acting as their rubber duck.

Another chunk of my time is spent in diplomacy with other people in the company and sometimes with customers.

Re: Ask HN: IT Directors and VP's – how do you manage your time and projects?

#23
What made you successful in the past may not make you successful today.

When I started to prioritize, delegate and only focus on key details, it was a big shift in mindset but also a big boost in my effectiveness as a VP.

Know when to say things and when not to say things. Let go and think big picture. You're in the business of delivering through your team and your role is about giving direction to your team so their work is meaningful to them and to the organization.

Not everything will need your attention - you mostly only need to know when the project will be completed, help your team unblock roadblocks (in terms of tech, process, people) and align all projects to the overall strategy.

Re: Ask HN: IT Directors and VP's – how do you manage your time and projects?

#24
post #9
post #8

You need to stop doing your old job and start doing your new job. That sounds obvious, but I see a lot of people get promoted and keep doing their old job, the one that they were so good at it and came so naturally. Even if the new person in your old job is only 25% as good as you are at, let/make them do it. Related, if you can see a better way to do it, strongly consider keeping your mouth shut if that way is only…

This is exactly the problem I see with my division's supervisor. He was a developer, and is now a program manager, but he wants to directly influence every single project instead of delegating. What is an effective way to encourage him to do his new job? This is impacting the team b/c he takes away lower level decision making responsibility, while not spending the time he needs to spend planning out and setting top l…

Well you have a few options. You'll have to gauge your own situation to see what you can get away with.

1) Ask him for his deliverables to you frequently. If he's a program manager, presumably part of his job is to fill you in on context and the goings on outside of your group. Ask him for those regularly. Ask him to present the planning and top level vision.

2) Be direct and tell him what you just wrote -- that you expect him to delegate and trust and not dictate now that he's been promoted.

Re: Ask HN: IT Directors and VP's – how do you manage your time and projects?

#25
post #7

This is not about time management at all. Many new execs mess this up -- it's not that you need to get more organized (or mostly not); you need to build a system that doesn't require you to intervene all the time. What this requires is - people you can trust - you actually trusting them - being able to identify relatively self-contained tasks you can delegate - being able to accept that you'll get less competent in t…

I think this is an excellent way to look at the situation.

From a psychological POV (e.g. ego & identity), this aspect was particularly significant to me as I moved from developer to manager to CTO and then CIO:

> - being able to accept that you'll get less competent in things you're delegating

Re: Ask HN: IT Directors and VP's – how do you manage your time and projects?

#26

It sounds like you're not delegating enough. This is key when you're managing, especially at a senior level. And not just technology-related stuff. Pick two thresholds: - Maximum amount of time you're willing to allocate to a specific task. (Example: 1h. FYI, David Allen of GTD fame recommends 5min for very senior execs.) Try to delegate anything above that number. - Amount of time you'll take you to get it done vs a…

> Build good-will and political capital in your organization.

It’s very easy to overlook relationship building. Even just stopping by, saying a quick hello, and giving a smile to execs in different departments can make a world of a difference in how well your departments can work together. This can make a big difference at whatever level you’re at in your career but is especially impactful the higher you go up the ladder.

Re: Ask HN: IT Directors and VP's – how do you manage your time and projects?

#27
1. Your calendar is your new todo list, if it doesn't fit, get rid of it. You're negotiating about your time. Review your calendar at the end of the week to ensure you're putting in time on the projects you need to.

2. You'll start to see why GTD got so popular, you need a list of things you can do. GTD's Agendas & WaitingFor lists are for you.

3. If you don't have an ea/admin you trust, you need to get on that. The best chief of staffs I've ever worked with started as EAs. They should be able to grow into HR, Finance, or Program Management, or chief of staff.

Re: Ask HN: IT Directors and VP's – how do you manage your time and projects?

#28
post #13

I'll steal a quote from Pittsburgh Penguins (American professional hockey) head coach Mike Sullivan: "Play the game the right way". Just do the right thing. Always. If you're not sure what that is, figure it out however you can, and do it. This time. Every time. Always. Once you start doing that, all the other BS melts away. A few personal thoughts of what "the right way" means in IT: - Treat everyone else like you w…

This is a great list; thanks for sharing!

Re: Ask HN: IT Directors and VP's – how do you manage your time and projects?

#29

Earlier quoted context omitted.

> strongly consider keeping your mouth shut if that way is only 5% better That's great advice. An experience with a director overruling his engineering staff is one reason I no longer work for him. As a leader, your most valuable asset is context : big-picture strategy, business priorities, and the like. If you're in an interaction where you find you're not utilizing that asset, you probably should back off and let y…

If the director is smarter and more knowledgeable about the engineering domain, he should overrule. that's what the big-picture strategy is all about, some people make it into leadership because they are really good and capable at engineering. So long as they stay sharp, they can still make technical decisions.

Everyone thinks they're smarter or more knowledgeable and will then always jump in

Re: Ask HN: IT Directors and VP's – how do you manage your time and projects?

#30
Your tasks and projects are now high level politics and people management. Give up thinking of technology, at all, you now have to maximise the value of Your department to the business and the perception of your VP counterparts. I found similar issues rising thru management and (I’m mid-career) have changed roles to focus on what I enjoy rather than politics.